X10
PRO 250Amp Coupler/Blocking Filter
Installs
at the electrical panel to couple up to three phases. Also prevents X10
command signals from entering or leaving the building, effectively isolating
the residence. Recommended for ALL X10 PRO installations. This device
CAN be retrofitted.
The X10 PRO 3-phase 250A Signal Blocking Coupler is designed to attenuate
(at a rate of 30:1) X10 power line carrier signals from crossing from
one household to another via the AC wiring. The coupler/blocker is installed
between the meter and the breaker panel, using the Copper Neutral between
the two. The unit may be used in single, dual or three phase installations.
For best results a PZZ01 should be installed at both homes experiencing
the signal crossings.
Unique features of the design include its ability to efficiently couple
X10 signals between phases, the elimination of any direct connections
to the power company-side wiring and the elimination of heavy current
carrying inductors, resulting in a very compact design.
Note: Installation must be carried out by qualified electricians
only. The main breaker must be turned off during installation and the
flter must be installed in a suitable workbox or equivalent enclosure.
Check local Electrical Codes in your area for any additional installation
requirements. A jumper on the PZZ01 is needed from L3 to L2 when installing
into a split-phase panel.
Installing the 250A Filter
- Switch off the
power at the main breaker panel.
- Install the filter
into a suitable workbox or equivalent enclosure using the four mounting
slots.
- Disconnect the
neutral cable running between the meter and the breaker panel/fuse box.
Pass the cable through the channel in the filter and re-connect it.
(Maximum 250 Amp Copper)
Note: If the cable is not long enough, use a new cable of the
correct type and rating. Do not attempt to extend the cable by joining
it.The cable must be passed through the filter in the correct direction
as indicated by the label on the side of the filter.
- Connect the N terminal
on the filter to neutral in the breaker panel using minimum 15A wire.
- Install a minimum
15A breaker or fuse in the breaker panel on phase 1 and connect it to
the filter terminal marked L1 using minimum 15A wire.
- Install a minimum
15A breaker/fuse to phases 2 and 3 as required and connect to terminals
2 and 3 on the filter.
- Check all wiring
and switch on the main breaker.
|